A BIM execution plan is where a project team commits, in writing, to how it will produce and manage information. This guide sets out what the plan should contain under ISO 19650-2:2018, how the tender-stage plan differs from the one used after appointment, and the mistakes that make a plan useless on site.
Ask About BEP SupportThe appointing party, usually the client or its representative, states what information it needs and when in the Exchange Information Requirements (EIR). The BIM execution plan (BEP) is the delivery team's answer. The EIR says what. The BEP says how, by whom, with what and by when.
ISO 19650-2:2018, the part of the standard that covers the delivery phase of an asset, places the plan at two points in the process. During tender response, the prospective lead appointed party establishes the delivery team's BEP so the client can judge the proposed approach. During appointment, the plan is confirmed with every task team and becomes the working document for the job. The two are often called the pre-appointment and post-appointment BEP.
| Pre-appointment BEP | Post-appointment BEP | |
|---|---|---|
| When | Submitted with the tender | Confirmed at appointment, then maintained through the project |
| Purpose | Lets the client assess the proposed approach, capability and capacity | Tells every task team how to work |
| Responsibility matrix | High level: which team produces which part of the model | Detailed: what information, by whom, to what level, at which milestone |
| Delivery plans | A delivery strategy | Task information delivery plans, combined into a master information delivery plan |
| Status | A proposal | Agreed by the whole delivery team, and updated when things change |
Templates differ, but a plan that covers the nine items below answers what ISO 19650-2 asks the delivery team to establish.
The project, the stages covered, and the named individuals who carry out the information management function for the delivery team and for each task team. Names, not job titles, because a plan with no names has no owner.
How the team will meet the EIR: the approach to collaboration, the objectives for producing information, the organisation of the team, and how the work is split between task teams.
How the information model is divided into separate models, by discipline, building, zone or level, and how those models are brought back together for coordination. This decides file sizes, who can work at the same time, and how clash detection is organised.
Which task team produces which elements of the model and which deliverables, developed after appointment into a detailed matrix that also states the level of information need and the milestone.
Naming of files and objects, classification, units, coordinates and origin, level of information need, model checking and approval routines. Where the client's standard already fixes these, the BEP records any additions or amendments the team proposes.
Authoring, coordination and review software with versions, exchange formats such as IFC and BCF, and the common data environment. Agreeing versions here avoids the upgrade made by one team halfway through that locks the others out.
Each task team's information delivery plan lists what it will issue and when. The lead appointed party combines them into the master information delivery plan, which is aligned with the design and construction programme.
An honest assessment of each task team's skills and resources, and the plan to close any gaps: training, recruitment, software, testing of the data environment and exchange methods before production starts.
The risks to delivering information on time, for example late design information, an untested exchange format or a single point of failure in the team, with the action and the owner for each.
Many plans state that clash detection will be carried out and stop there. A plan that works on site also states which model pairs are tested, at what tolerance, how often, who chairs the coordination meeting, how issues are tracked and what counts as resolved. That is the clash matrix and the coordination cycle, and it belongs in the BEP or in an appendix to it.
A plan that still names the previous client's team, software versions or zones tells the reader nobody checked it.
The client already knows what it asked for. The plan has to say how the team will deliver it.
Fabrication-level models at concept stage cost money and slow the team down. State the level of information need per stage.
Roles without names cannot be held to anything. Update the names when people change.
The first IFC export should not happen in the week of the first submission. Test the exchange during mobilisation.
The plan is a live document. Review it at each stage and whenever the team, scope or software changes.
Alftek prepares BIM execution plans as part of its BIM consultancy in Qatar, and works to the plan agreed with the project team on every modeling and coordination engagement. Our workflows are aligned with ISO 19650.
How the standard's requirements are applied on Qatar projects.
Explore ISO 19650 BIM in Qatar →BEP, implementation planning, templates and standards, and QA/QC.
Explore BIM Services in Qatar →The clash matrix and coordination cycle the plan describes, run for you.
Explore Clash Detection →Architectural, structural and MEP models produced to the plan.
Explore BIM Modeling in Qatar →Source and further reading: ISO 19650-2:2018, Organization and digitization of information about buildings and civil engineering works, including building information modelling (BIM), Information management using building information modelling, Part 2: Delivery phase of the assets. The UK BIM Framework publishes free guidance on applying it. This guide is a summary for orientation and does not replace the standard or your contract.
A BIM execution plan (BEP) is the document in which a delivery team explains how it will manage and produce the information a project requires. It answers the appointing party's information requirements: who does what, to which standards, in which software, in what order and by which dates.
The pre-appointment BEP is submitted with the tender and shows how the team proposes to manage information, so the client can assess the approach, capability and capacity. After appointment the same plan is confirmed and developed in agreement with every task team, and it becomes a live project document supported by the detailed responsibility matrix and the information delivery plans.
Under ISO 19650-2 the lead appointed party establishes the delivery team's BEP, with input from each task team. On a Qatar building project that is typically the lead consultant at design stage and the main contractor at construction stage. A BIM consultant can draft and maintain it on their behalf.
No. The Exchange Information Requirements are written by the appointing party and state what information is required and when. The BEP is the delivery team's response and states how that information will be produced and managed.
As long as it needs to be to remove ambiguity, and no longer. A plan that people actually open is worth more than a thorough one nobody reads. Put standards, schedules and matrices in appendices and keep the body of the plan to the decisions the team has to follow.
Whenever the team, the scope, the software or the programme changes, and at the start of each project stage. A BEP that still describes the tender-stage team during construction is a common audit finding.