LOD 100 to 500: What You Receive at Each Level

"Model it to LOD 300" appears in almost every BIM scope, and it is read differently by almost everyone who signs one. This guide explains what each level from LOD 100 to LOD 500 actually contains, what you can and cannot use a model for at each level, and how to write an LOD requirement that a modeling team can price and deliver.

Ask About Modeling Scope

Level of development, not level of detail

LOD is usually expanded as Level of Development. It describes how far the geometry and the information attached to a model element have been worked out, and therefore how much other people can rely on it. Level of Detail, the other common reading, only describes how much graphic detail is drawn. A beautifully rendered generic chair can still be LOD 100, because nobody has decided which chair it is.

The levels used today come from the American Institute of Architects' BIM protocols and are defined element by element in the LOD Specification published by BIMForum, which added LOD 350 between 300 and 400. Most scopes in the Gulf use these numbers, even on projects that otherwise follow ISO 19650.

The single most useful rule: LOD belongs to an element at a milestone, not to a whole model. "An LOD 300 model" is shorthand that hides the real question, which is which elements reach which level, by when, and who develops them.

What each level contains

The descriptions below summarise the general definitions. The BIMForum specification gives element-by-element examples, and your client's standard or the project's BIM execution plan may refine them.

LevelWhat the element isReliable forNot reliable for
LOD 100
Concept
The element is shown as a symbol, a mass or a generic placeholder. Its existence and rough position are known; its size, shape and type are not.Massing studies, early area and cost estimates per square metre, site and orientation decisionsMeasuring quantities or dimensions from it
LOD 200
Schematic
A generic element with approximate size, shape, location and orientation, for example a wall of an assumed thickness or a duct of an approximate size.Option studies, early system layouts, approximate quantitiesCoordination, setting out, ordering
LOD 300
Detail design
A specific element: size, shape, location and orientation can be measured directly from the model without relying on notes or drawings.Design coordination, clash detection between major elements, quantities for estimating, detail design drawingsFabrication and installation detail
LOD 350
Coordination
LOD 300 plus the parts needed to coordinate with neighbouring systems: supports, hangers, connections, openings and clearances.Trade coordination, sleeves and openings, clearance and access checksShop-level fabrication
LOD 400
Construction
Enough detail and accuracy to fabricate, assemble and install the element: exact sizes, connections, fixings and the information a trade needs to build it.Shop drawings, prefabrication, installation sequencingTreating it as a record of what was built
LOD 500
As-built
The element has been verified against what was installed on site, in size, shape, location, quantity and orientation.Record models, handover, facility management and future renovationAssuming it contains more geometry than LOD 400

Two levels are often misunderstood. LOD 350 matters more than its position in the list suggests: it is the level at which supports, connections and openings exist, and so the level at which most of the clashes that cost money on site become visible. LOD 500 is not a sixth step of extra geometry. It is a statement that the element has been checked against the installed work, which is why the BIMForum specification does not treat it as a further stage of development.

Which LOD at which project stage

A typical progression on a building project looks like this. Real projects vary by element: structure usually runs ahead of MEP, and loose furniture may never pass LOD 200.

Concept and massing: LOD 100

Volumes, levels and grids to test the brief, the site and the budget. Cost is estimated per square metre, not measured from elements.

Schematic design: LOD 200

Generic walls, slabs, columns and main service routes with approximate sizes. Enough to compare options and reserve space for plant and risers.

Detail design: LOD 300

Specific sizes and positions for the main elements of every discipline, so drawings can be taken from the model and the first coordination runs mean something.

Pre-construction coordination: LOD 350

Supports, hangers, connections, sleeves and access zones added, and the trades coordinated against each other before shop drawings start.

Construction: LOD 400

Fabrication and installation detail, normally developed by the contractor or the trade that builds the element, and used for shop drawings and prefabrication.

Handover: LOD 500

The model is updated to match the installed work and verified on site, then handed over with the asset information the operator needs.

How to specify LOD so it can be priced

A requirement a modeling team can quote against has four parts. Leave any of them out and two honest bidders will price two different jobs.

LOD and ISO 19650: ISO 19650 does not use LOD numbers. It asks for the level of information need, which defines the geometry, the alphanumeric information and the documentation required for each purpose. The concept is set out in EN 17412-1, adopted internationally as ISO 7817-1. On many projects the LOD table survives as a practical shorthand inside that framework. What matters is that the BIM execution plan states clearly which one the project uses. See how we apply ISO 19650 on Qatar projects.

Five LOD mistakes that cost money

"Everything to LOD 500"

A blanket requirement in a tender either inflates every price or gets ignored. Ask for the level each element needs at each stage.

LOD 400 from the designers

Fabrication detail depends on the products and methods the contractor chooses. Asking designers for it duplicates work that the trades will redo.

Coordinating LOD 200 models

Clash runs on generic models produce long reports of conflicts that will move anyway. Coordination pays off from LOD 300, and most of all at LOD 350.

Graphics mistaken for reliability

A detailed-looking family can sit at an unverified position. Judge an element by what has been decided about it, not by how it renders.

As-built without verification

A construction model renamed "as-built" is not LOD 500. Without a survey or a site check, the operator inherits the design intent, not the building.

How Alftek works with LOD

Alftek models in Revit from LOD 100 to LOD 500 for Qatar projects, to the level each stage actually needs rather than to the same depth everywhere: LOD 300 for detail design, LOD 400 with shop drawings for construction, and LOD 500 record models updated to as-installed conditions for handover. When you send drawings or BIM requirements, our proposal states the LOD for each stage.

BIM modeling

Architectural, structural and MEP models developed to the agreed LOD.

Explore BIM Modeling in Qatar →

Coordination

Clash detection run at the level where it pays off.

Explore Clash Detection →

As-built and record models

Drawings and models updated to match what was built.

Explore As-Built Drawings →

Existing buildings

Point cloud to BIM when there is no reliable model to start from.

Explore Scan to BIM →

Sources and further reading: BIMForum, Level of Development (LOD) Specification, published annually with element-by-element definitions and illustrations. American Institute of Architects, G202-2013 Project Building Information Modeling Protocol Form. EN 17412-1 / ISO 7817-1, Level of information need. This guide is a summary for orientation; your contract, the client's BIM standard and the project's BIM execution plan take precedence.

Frequently asked questions

What does LOD mean in BIM?

LOD usually stands for Level of Development: how far the geometry and information of a model element have been worked out, and so how much the rest of the team can rely on it. It is sometimes read as Level of Detail, which only describes how much graphic detail is shown. The two are not the same thing.

Is LOD 500 more detailed than LOD 400?

Not necessarily. LOD 500 describes a model that has been checked against what was actually built, so it is about verification, not more geometry. An as-built record model at LOD 500 can carry less fabrication detail than an LOD 400 model used to build from.

What LOD is needed for clash detection?

Meaningful coordination usually starts at LOD 300, when sizes and locations are specific. LOD 350 adds supports, connections and interfaces between systems, which is where many real clashes are found. Running clash tests on LOD 200 models mostly produces noise.

Does a whole model have one LOD?

No. LOD applies to model elements, not to the model as a whole. At any milestone, the structure may be at LOD 300 while the MEP is at LOD 200 and the furniture at LOD 100. That is why LOD is specified in a table by element and by stage.

What is the difference between LOD and the level of information need?

LOD comes from the BIMForum LOD Specification and the earlier AIA protocols. ISO 19650 instead uses the level of information need, which states the geometry, the alphanumeric information and the documentation required for each purpose and milestone. On a project working to ISO 19650, the LOD table is often kept as a convenient shorthand inside that framework.

Who decides the LOD for each element?

The client's information requirements set what is needed at each milestone, and the delivery team commits to it in the BIM execution plan and its responsibility matrix, which names the team that develops each element and the stage at which it reaches each level.